Milton District Hospital

The Milton District Hospital project consisted of a redevelopment/building addition on the site of the existing Milton District Hospital. It comprised of new roads, parking and walkways around a new 360,000 sf acute care facility.

The project had a total gross floor area of approximately 360,000 sf. CPS Flooring completed the project on time. Quartz flooring was used in washrooms and operating rooms, while a waterproofing product was used in the mechanical rooms. CPS also provided floor levelling systems throughout the entire building.

Areas of work: Patient Washrooms, Operating Theatres and Mechanical Rooms

Products used: Quartz Flooring, Mechanical room waterproofing

Project Lead: Doug Kurtin

Contractor: PCL


Location: Milton District Hospital Р7030 Derry Road, Milton, ON